Ewing Schools Announce Referendum '18 Phase 2 Projects/Schedule
IMMEDIATE RELEASE
January 22, 2020
Ewing Schools Announce Referendum ’18 Phase 2 Projects/Schedule
In October of 2018, the Ewing Township community supported the School District’s Referendum ’18 vote. The referendum consisted of a series of district-wide facility projects designed to create healthier, safer, and more modern schools for the students of the school community.
Since this landmark vote, the school district has completed its Referendum ’18 Phase 1 projects along with several other facility projects that were previously scheduled and budgeted:
COMPLETED REFERENDUM PROJECTS
- Roof Replacement at Parkway and O’Brien Academy
- Roof Replacement at Lore
- District-Wide Security & Communications Projects
- Interior Classroom/Bathroom Renovations at Antheil and Lore
- District Tennis Courts at Antheil
- Ewing High School Parking Lot Expansion
- Ewing High School Multipurpose Field Staircase replacement
COMPLETED NON-REFERENDUM PROJECTS
- Ewing High School Multipurpose Field Replacement and Storm Water Drainage Repairs
ONGOING NON-REFERENDUM PROJECTS
- Targeted office facility renovations at the Gusz building, expected completion February of 2020
With completion of these projects, the school district is set to embark on its schedule for Referendum ’18 Phase 2 projects. Please review the chart below for a district-wide overview:
2020 REFERNDUM ROUNDUP – PHASE 2
EWING HIGH SCHOOL PROJECTS
Description |
Bid |
Start |
Anticipated Completion |
Fire Alarm System replacements |
Jan. 20 |
Apr. 20 |
Summer 20 |
Controls, HVAC Improvements, Boiler & Chiller Replacements, asbestos abatement as needed |
Jan. 20 |
Summer 20 |
Summer 21 |
Targeted toilet room and classroom renovations, interior & exterior door replacements, security keying enhancements |
Jan. 20 |
Summer 20 |
Fall 20 |
North and South Gymnasium and Locker Room Renovations |
Jan. 20 |
Apr. 20 |
Fall 20 |
Athletic Site improvements including baseball field improvements, ball stopper, backstop, scoreboard, and overall site ADA compliance improvements |
Jan. 20 |
Summer 20 |
Summer 20 |
Operational Impacts:
- Due to the HVAC improvements and classroom renovations, throughout the construction phase a small bank of classrooms may need to move throughout the year. The district will make every effort to minimize the disruption to the educational process.
- For the duration of the Gymnasium and Locker Room Renovations, these areas will be unavailable for use. The Principal, Athletic Director, and Physical Education Department have prepared a plan that will address the need for space during that time.
- For the duration of the Athletic Site and Baseball field improvements, those areas may be periodically unavailable throughout the construction period.
- The Fisher Middle School Moving-Up ceremony which typically would take place in the Ewing High School North Gym will be scheduled to take place outside on the EHS Athletic Complex on Tuesday, June 16th at 6:30PM (Please note the change of date) with a rain date of Wednesday, June 17th. The Fisher administration will provide more detailed information shortly.
- Additionally, due to the need for a safe construction staging space there will limited access to the back parking lot of the High School behind the gyms for the duration of these projects.
FISHER MIDDLE SCHOOL PROJECTS
Description |
Bid |
Start |
Anticipated Completion |
Chiller replacement |
Jan. 20 |
Winter 20 |
April 20 |
Roof replacement/restoration |
Jan. 20 |
Summer 20 |
Summer 20 |
Fire Alarm System replacements |
Jan. 20 |
Apr. 20 |
Summer 20 |
Controls, HVAC Improvements, Boiler Replacements, asbestos abatement as needed |
Jan. 20 |
Summer 20 |
Summer 21 |
Targeted toilet room and classroom renovations, interior & exterior door replacements, security keying enhancements |
Jan. 20 |
Summer 20 |
Fall 20 |
Gymnasium and Locker Room Renovations |
Jan. 20 |
Summer 20 |
November 20 |
Walking track pavement improvements |
Jan. 20 |
Summer 20 |
Summer 20 |
Operational Impacts:
- Throughout the summer, the interior of the school building may be off-limits in areas affected by the roof replacement. Staff will be relocated as needed.
- Due to the HVAC improvements and classroom renovations, throughout the construction phase a small bank of classrooms may need to move throughout the year. The district will make every effort to minimize the disruption to the educational process.
- For the duration of the Gymnasium and Locker Room Renovations, these areas will be unavailable for use. The Principal, Athletic Director, and Physical Education Department have prepared a plan that will address the need for space during that time.
RYAN BUILDING/ O’BRIEN ACADEMY PROJECTS
Description |
Bid |
Start |
Anticipated Completion |
Fire Alarm System Replacement |
Jan. 20 |
Sep. 20 |
Summer 21 |
Interior/Exterior door replacements, security keying enhancements |
Jan. 20 |
Sep. 20 |
Summer 21 |
HVAC Controls and equipment replacement |
Jan. 20 |
Summer 20 |
Summer 21 |
Operational Impact:
- Minimal operational impact is anticipated. There may be periodic times throughout the summer that HVAC systems may need to be shut down. Arrangements to move staff will be made as needed.
ANTHEIL ELEMENTARY SCHOOL PROJECTS
Description |
Bid |
Start |
Anticipated Completion |
Boiler replacement |
Jan. 20 |
Summer 20 |
Summer 20 |
Chiller replacements |
Jan. 20 |
Winter 20 |
April 20 |
Fire Alarm System Replacement |
Jan. 20 |
Apr. 20 |
Summer 20 |
Operational Impact:
- Minimal operational impact is anticipated. There may be periodic times throughout the summer that HVAC systems may need to be shut down. Arrangements to move staff will be made as needed.
LORE ELEMENTARY SCHOOL PROJECTS
Description |
Bid |
Start |
Anticipated Completion |
Controls, HVAC Improvements, Boiler replacements, and asbestos abatement as needed |
Jan. 20 |
Summer 20 |
Summer 21 |
Operational Impact:
- Due to the HVAC improvements and classroom renovations, throughout the construction phase a small bank of classrooms may need to move throughout the year. The district will make every effort to minimize the disruption to the educational process.
PARKWAY ELEMENTARY SCHOOL PROJECTS
Description |
Bid |
Start |
Anticipated Completion |
Boiler replacement |
Jan. 20 |
Summer 20 |
Summer 20 |
Chiller replacements |
Jan. 20 |
Winter 20 |
March 20 |
HVAC Controls and equipment replacement |
Jan. 20 |
Summer 20 |
Summer 21 |
Operational Impact:
- Due to the HVAC improvements and classroom renovations, throughout the construction phase a small bank of classrooms may need to move throughout the year. The district will make every effort to minimize the disruption to the educational process.
GUSZ BUILDING PROJECTS
Description |
Bid |
Start |
Anticipated Completion |
Roof Replacement /Restoration and exterior doors |
Jan. 20 |
June 20 |
July 20 |
Operational Impact:
- Throughout the summer, the interior of the Gusz building may be off-limits in areas affected by the roof replacement. The project will impact district operations as some Gusz personnel may need to be temporarily relocated to other school buildings.
“It is certainly an exciting time as we move forward with these projects to improve our facilities,” Superintendent Michael Nitti stated. “That being stated, these endeavors will most certainly impact our operations and we greatly appreciate the cooperation and understanding of the school community as we work to make our schools better places for our students to learn and grow.”
“We continue to be appreciative of the support of the community for our Referendum ’18 endeavors,” School Business Administrator Dennis J. Nettleton added. “The positive impact of our Phase 1 projects is already tangible, and although we recognize the challenges ahead, we are excited to embark on our Phase 2 initiatives and see the benefits for our school community.”
Superintendent Nitti and Mr. Nettleton will present on these projects at the January 27th Board Meeting to be held at the Parkway Elementary School.