Referendum Roundup '18 August 2019 Update: Phase 1

August 2019 Referendum Roundup Update: Phase 1 

BP-1 Roof Replacement at Parkway and Ryan (O’Brien Academy); Strober-Wright Roofing

  • Parkway:  Roofing work is complete. Installation of roof accessories, flashing, and metal work is ongoing. Masonry and caulking repairs to begin shortly.
  • Ryan (O’Brien Academy):  Roofing work is complete. Installation of roof accessories, flashing, and metal work is ongoing. Masonry repairs to begin to begin shortly. 

BP-1A Roof Replacement at Lore; VMG Group

  • Roofing cap sheet to be complete early next week. Installation of roof accessories, flashing, and metal work is ongoing. 

BP-2 District Wide Communications Projects; Millennium Communications and ePlus

  • Millennium has completed 100% of their original contract camera and security access work.
  • Millennium’s Change Order work, additional cameras, to begin immediately upon receipt of materials.
  • ePlus has completed approximately 75% of their wiring and installation of new speakers and message displays. Their progress was delayed by added work supporting the existing above ceiling electrical work in Antheil’s classrooms being renovated to code, which was done on a Time and Material basis.

 BP-3 Interior Renovations at Antheil and Lore; Aliano Brothers

  • Antheil: Selective demolition and painting are complete. Lighting, plumbing installations, glazing replacements, ceramic tile, ceiling tile, and framing are ongoing. Classroom vinyl floor installation to be complete this week.
  • Lore: Selective demolition and painting are complete. Lighting, plumbing installations, glazing replacements, and ceiling tile are ongoing.

 BP-4, District Tennis Courts at Antheil and High School Parking Lot; Flanagan’s Contracting

  • DTC @ Antheil: Tennis court paving, concrete work, and drainage are complete. Parking lot paving to be complete next week. Installation of lighting conduit, tennis court fencing, and site restoration is ongoing.
  • EHS: Drainage work is complete. Paving commenced on 8/15/2019 and scheduled to be complete 8/23/2019. Site restoration is ongoing.

 EHS Track, Field, Drainage; Field Turf

  • Decommissioning of the existing drainage commenced on 8/14/2019 and will be complete in approximately a week.
  • Change Order work, installation of new long jump and lacrosse backstop netting, is ongoing.
  • Site restoration is ongoing.
  • Artificial turf installation scheduled to begin on 8/26/2019.