Referendum Roundup '18 June 2019 Update: Phase 1

June 2019 Referendum Roundup: Phase 1 Update 

Roofing Replacement Projects 

  • Parkway Elementary School – Overlay 45,000 Square Feet of Roofing
  • Contract Awarded to Strober-Wright, construction to start on or about June 24, 2019 
  • Lore Elementary School – Overlay 29,000 Square Feet of Roofing
  • Contract Awarded to VMG Group, construction to start on or about June 24, 2019. 
  • O’Brien Academy – Overlay 4,900 Square Feet of Roofing
  • Contracts Awarded to Strober-Wright, construction to start on or about June 24, 2019. 

District-Wide Communications & Security Upgrades 

  • Update
  • Camera installations 100% complete at Parkway, Lore, & Antheil
  • Camera installations 80% complete at Fisher/OBA
  • Rough-in wiring for PA system/clocks 100% complete at Parkway Fisher/Ryan and EHS. 

Antheil Elementary School Toilet Room/Classroom Renovations/Doors – Phase 1 

  • Update
  • Moving company engaged to move boxes & furniture out June 19-21
  • Demo and construction to commence June 24, 2019 

Tennis Court Construction @ Antheil Elementary & Parking Lot Construction at EHS 

  • Update
  • Field mobilization commenced on June 1 at AES and June 19 at EHS.
  • Construction is ongoing

Non-Referendum Funded Project Progress Updates 

Ewing High School Athletic Facility and Drainage Improvements 

  • Update
  • Installation of temporary fencing & facilities
  • Delivery of piping and precast materials
  • Excavation, installation of piping and structures approximately 25% complete
  • Removal of old Turf Field completed