Posted 10/01/2017: Timeline of Referendum Activities

 

The Ewing Public Schools

 

Timeline of Referendum Activities

 clock tower

 

Description

 

Estimated Timeframe

 

Data Gathering and Collaborative Process

 

May through August 2017

 

School District/Stakeholder/Design Team Interactions

 

July through September 2017

 

Public Roll-Out and BOE Review of Proposed Projects

 

September through November - 2017

 

Approval of Scope, Costs, and Final Form of Proposal

 

December – 2017

 

NJDOE and Planning Board Submission Period

 

January – 2018

 

Referendum Communication Plan/Process

 

February through September – 2018

 

Conduct Referendum

 

September 25, 2018

 

If Successful

 

 

Develop Project Timeline

 

October - 2018

 

Construction Phase

 

 

     Roofing/Selected Facility Projects

Summer – 2019

     Rehabilitation Projects – Phase 1

Summer – 2019

     Rehabilitation Projects – Phase 2

Summer – 2020

     Additional Renovation Projects

2020-2021